- 1912 or +91471 2555544
Objective:
To explore and optimally develop renewable energy resources in the State so as to meet the electricity demand in future and to save electrical energy through energy efficiency measures and Demand Side Management.
Functions:-
Important Orders / Circulars / Technical Specifications related to Solar power plants
Present Activities
(a) Renewable Energy Projects.
The project proposals are divided in to three categories:
ideation stage - done to prove the idea /concept only - upto Rs 75,000/-
Pilot project - after ideation to evaluate potential, feasibility, performance - upto Rs.15,00,000/-
Commercialisation - after piloting successfully - upto 50,00,000/-
Contact Address: Cabin No.918, Vydyuthi Bhavanam, Pattom.P.O, Tvpm-4
Contact Mail - This email address is being protected from spambots. You need JavaScript enabled to view it.
Contact Number - Innovation Group - 0471 2514421,
AEE – 9496012417, AEE – 9496012416, AE - 9446008965
(c) ESCOT (Energy Savings and Coordination Team)
Organisation Chart (Click to Enlarge)
Status of Solar Projects
1.COMPLETED SOLAR PROJECTS OF KSBL
Sl no. |
Name of the projects |
Installed capacity (MW) |
Date of completion |
1 |
Kanjikode Ground mounted grid connected solar projects in the premises of sub station |
1.00 |
20.08.2015 |
2 |
Roof top solar projects of households in tribal colony, Chalayoor |
0.096 |
31.08.2015 |
3 |
Roof top grid connected solar projects on the buildings of Porigalkuthu power house |
0.050 |
10.09.2015 |
4 |
Floating solar- Banasura sagar reservoir |
0.010 |
21.01.2016 |
5 |
Solar tree, solar fountain, solar flower and solar canopy in the premise of Banasura sagar reservoir |
0.003372 |
21.01.2016 |
6 |
Kollamgode ground mounted grid connected solar projects in the premises of sub station |
1.00 |
08.08.2016 |
7 |
Padinjarethara Dam Top grid connected solar power project. |
0.40 |
29.08.2016 |
8 |
Edayar ground mounted grid connected solar projects in the premises of S/Sn and section office. |
1.25 |
05.09.2016 |
9 |
Roof top grid connected projects on the buildings of Generating stations-17 nos. |
0.7 |
07/2017 |
10 |
Roof top solar projects of 5 tribal colonies of Palakkad (D.D.G) |
0.047 |
27.10.2016 |
11 |
Barapole canal bank grid connected solar project. |
1.00 |
07.11.2016 |
12 |
Barapole canal top grid connected solar project. |
3.00 |
17.11.2016 |
13 |
Roof top solar project in 2 tribal colonies of Palakkad (D.D.G) |
0.018 |
30.11.2016 |
14 |
Thalakkulathoor, Kozhikode Ground mounted grid connected solar project |
0.65 |
22.04.2017 |
15 |
Grid connected Roof top solar projects on Suitable buildings of KSEBL Transmission wing (27 no.) |
0.910 |
02/2018 |
16 |
Grid connected Roof top solar projects on Suitable buildings of KSEBL Distribution wing (12 no.) |
0.46 |
21.12.2017 |
17 |
Grid connected Roof top solar project on 10th floor of Vythuthi bhavan , Trivandrum |
0.03 |
17.05.2017 |
18 |
Manjeshwaram Ground mounted grid connected solar project in the S/Sn premises. |
0.50 |
30.05.2017 |
19 |
Kuttippuram Ground mounted grid connected solar project in the S/Sn premises. |
0.50 |
28.11.2017 |
20 |
Banasurasagar reservior/kakkayam grid connected floating solar project |
0.50 |
04.12.2017 |
21 |
Pezhaykkapalli-Moovattupuzha,Ernakualm Ground mounted grid connected solar project in the S/Sn premises. |
1.25 |
15.01.2018 |
22 |
Pothencode Ground mounted grid connected solar project in the S/Sn premises. |
2.00 |
02.02.2018 |
23 |
Peerumedu,Idukki Ground mounted grid connected solar project in the S/Sn premises. |
0.50 |
23.04.2018 |
Total |
15.874372 |
||
On grid consumers of KSEBL |
18.867 |
As on 30-06-2018 |
2. OTHER COMPLETED SOLAR PROJECTS IN KERALA
Sl no. |
Name of the projects |
Installed capacity (MW) |
Date of completion |
1 |
CIAL |
30 |
11.12.2017 |
2 |
IREDA |
50 |
14.09.2017 |
3 |
ANERT |
2 |
09.12.2016 |
4 |
Hindalko |
1 |
31.03.2016 |
Total |
83 |
||
Total capacity of all the Solar projects in Kerala |
117.741372 |
ONGOING PROJECTS OF KSEBL
Sl. No. |
Name of the Project |
Capacity (MW) |
Current Progress |
1 |
Ponnani, Malappuram ground mounted project |
0.50 |
Construction in progress (Expected to be completed in 2018-19) |
2 |
Kozhikode Dist. Panchayath |
0.480 |
Zero progress. Only SLD approved. Other documents have not been submitted. |
2 |
Kannur Dist. Panchayath I phase |
0.670 |
Structures and panels despatched at site. FAT for inverter has been arranged. |
3 |
Kasargode Dist. Panchayath-I phase |
0.195 |
Site handed over to M/s PENA Ltd on 19.07.2018. Zero progress. No documents have been submitted by the contractor. |
4 |
Kasargode Dist. Panchayath-II phase |
0.335 |
Site handed over to M/s INKEL on 12.09.2018. |
5 |
Government Institutions South (NCESS, Attingal Municipality, Kuriyottumala Buffalo Breeding Farm) |
0.0575 |
Erection under progress |
6 |
Malappuram District Panchayath |
0.110 |
SLD approved. Directed M/s LV Solar Solutions to resubmit the schematic diagram and structural diagram |
7 |
Roof top solar project at Attingal 2nd phase, Kollam and Kottayam |
0.133 |
Waiting for rock bottom rate
|
8 |
Roof top solar project at Attingal - 3rd phase |
0.056 |
Corrected MoU submitted to Secretary, Attingal Municipality for approval |
9 |
Roof top project at LSGD, Wayanad. 72 kWp 3 locations
|
0.072 |
Tender cancelled. Re- tender to be floated on 25.09.2018 |
10 |
LSGD Thiruvananthapuram (LSGD)
|
0.490 |
Dist Panchayath TVM remitted 3.355 Cr to KSEBL in Mar 2018. Solar survey and cost estimation completed in all locations. DPR preparation in the final stage. |
11 |
Kannur – LSGD 2nd phase -450 kWp at 29 locations |
0.450 |
DPR forwarded. Decision of council to be obtained. Fund of Rs. 2.74 Cr received |
12 |
Kasargode Dist. Panchayath-III phase |
0.135 |
DRP approved by LSGD. Amount has not been remitted yet. |
13 |
Kannur –LSGD 3rd Phase |
|
Survey going on at 11 sites. |
14 |
Buffalo breeding farm, Kuriottumala - 2nd phase |
|
DPR under preparation |
15 |
Kasargod District Planning office –Implementation of 60 kWp grid connected Solar plant |
0.065 |
Draft MoU between KSEBL and DPO, Kasargode has been forwarded to DPO, Kasargode for signing and return. The same is not yet received. |
16 |
Attapadi Goat Farm (Agali) |
0.500 |
Meeting conducted on 11.09.2018 and discussed the implementation procedure with President, District Panchayath, Palakkad. Decided a visit on 27.09.2018 for preparation of detailed project report. |
17 |
CUSAT, 1 MWp |
1.000 |
Feasibility Survey Pending |
18 |
Poringalkuthu IB 2kWp |
0.002 |
Survey Pending |
19 |
Calicut University, 57kWp. 50 Lakh |
0.057 |
Rs 50 lakh received on 25.06.2018. Signed MoU not received even after reminder |
20 |
KUHS, 250 kWp |
0.250 |
Ground mounted |
21 |
Nadakkavu, 24 kWp |
0.024 |
DPR submitted |
22 |
Shornur VB |
|
Survey completed, DPR under preparation |
23 |
Panmana Grama Panchayath, 5kwp or less |
|
Survey completed DPR under preparation |
24 |
Mokeri School |
|
Survey Pending |
25 |
300 Wp AC solar plant of Adtech |
|
Technical data pending from M/s Ad tech |
26 |
Govt H.S Perinjamkutty. Vathikudi Grama Panchayath |
|
Survey Pending |
27 |
Thrissur Govt. Medical college 765kWp 5.85.Cr |
0.765 |
Fund not received |
28 |
Govt. Engineering College Kannur , Ground mounted , 150kWp, 87.3 lakh |
0.150 |
Fund not received |
29 |
Roof covering on open terrace of new constructed building of ES Perambra for installation of solar plant |
|
Technical feasibility and design data sent to Dy CE, EC, Vadakara, Pending report from EC Vadakara |
30 |
Taluk Hospital Koyilandi , 30kWp |
0.030 |
Structural design pending |
31 |
District court Kalpetta |
|
Survey completed, DPR under preparation |
32 |
Govt High School, Meppadi |
0.010 |
DPR submitted |
33 |
Roof top solar projects in the buildings under Directorate of Technical education |
0.050 |
Discussions going on to finalize the projects |
34 |
Ettumanur, Kottayam Ground mounted projects |
1.00 |
Work started but held up due to Wet land issue |
35 |
Nenmara Ground mounted project |
1.5 |
To be re tendered |
36 |
Medical College Trivandrum roof top project |
0.3 |
To be completed in 2018-19 |
37 |
Parippally Medical College roof top project |
0.9 |
To be completed in 2018-19 |
38 |
Brahmapuram Ground mounted project |
6.5 |
To be completed in 2019-20 |
39 |
Agali Ground mounted project |
1 |
To be completed in 2019-20 |
40 |
Kanjikode Ground mounted project |
2 |
To be completed in 2019-20 |
|
Total |
20.3315 |
|
|
Soura scheme |
1000 MW |
To be Completed within three years |
West Kallada Floating Solar Project by M/S NHPC |
50MW |
10 MW will be completed in the first Stage with VGF of Rs.13.8 Crores from Govt. of Kerala. |