- 1912 or +91471 2555544

Transmission

Transmission network, the backbone of any power system enables transfer of bulk power from the generating stations to the load centers. Over the years the intra state transmission infrastructure in Kerala has grown substantially with the addition of more and more EHT substations and lines. The Kerala grid is presently connected to the national grid mainly through three 400 kV double circuit lines viz. (1) Udumalpett – Madakkathara, (2) Thirunelveli – Pallippuram (Trivandrum).

The transmission sector of KSEB Ltd is geographically divided in to two zones – the North Zone headquartered at Kozhikode and the South Zone headquartered at Thiruvananthapuram. Each zone is headed by a Chief Engineer. In addition to the above, the System Operations wing which performs the real time management of Kerala Power System also comes under the Transmission SBU. The System Operations wing is headed by a Chief Engineer and is headquartered at Kalamassery.

Transmission

The Kerala grid has grown considerably during the recent years. We have as many as 375 Substations spread across the state as on 30.06.2015. Also the total length of our transmission network is 11814.251 Ckm. The total power transfer capacity of our Substations stands at 17,548 MVA.

An abstract view of the transmission system of the State is given in the table below.

Sl No

Voltage

No of Substations

Line length in Circuit kms

1

400 kV

1+4*

*837.4

2

220 kV

19

2797.536

3

110 kV

140

4347.29

4

66 kV

76

2145.51

5

33 kV

135

1686.515

(* - Substations and lines owned by PGCIL)

System Operation

The Kerala power system recorded a maximum peak demand of 3602 MW on 26.3.2015, where as the morning demand rose to 3072 MW on 6.04.2015. The daily consumption of the state reached a maximum of 70.99 MU on 26.3.2015. A notable change in the load pattern of the Kerala power system is the flattening of the load curve during the recent years. ld control room

The system operation wing was able to manage the grid with out load shedding since June 2013 through meticulous planning and effective management of the system even on the face of increasing power prices and while the rest of the country was reeling under severe power cuts. This was achieved by exploring market opportunities and also through efficient utilization of the hydro resources.

Apart from the effective management of the system, the system operation wing performs other functions such as the SCADA up gradation project, modernization of the protection system of EHT Substations, Routine/Pre-commissioning/ Commissioning / Testing and trouble shooting of all type of Substation equipments, maintenance of communication equipment etc.