|  Visit Old Website

Sengulam Power Station

Capacity - 4x12.7 MW

In the case History of Power development in Kerala State, the first Power Project was Pallivasal Hydro Electric Project, and it was commissioned in 1940. The Sengulam Hydro Electric Project commissioned in the year 1954 was the next project soon after the commissioning of Pallivasal Project. In other words, Sengulam Project was mainly intended to utilize the tailrace water of Pallivasal Project. For this purpose, Sengulam balancing Reservoir was formed by constructing a dam at Sengulam. This Reservoir is of low storage capacity - 2.31 MCM (Dead storage – 1.61MCM + effective storage-0.70MCM). The water level of Sengulam Balancing Reservoir is 10 M higher than the tailrace level of Pallivasal Project. So a pump house is provided at Pallivasal Power House to pump the tail water (of PHEP) to the Sengulam Balancing Reservoir. The water level in the Sengulam Balancing Reservoir is kept within the limits carefully to avoid spilling over of the dam. The Sengulam Generating Station is located at Vellathooval Panchayath on the right bank of Muthirapuzha river. This project is one among the projects of “Muthirapuzha basin” which is the cascaded arrangements of Maduppetty, Pallivasal, Sengulam, Panniar, Neriamangalam and Lower Periyar Hydro Electric Projects.
There are 4 Nos. of machines each having a capacity of 12.7 MW. The turbines used are of Horizontal axis double runner Pelton type.
The renovation works of this station was carried out during the period of 2001-2002, as the part of Panniar- Pallivasal-Sengulam Hydro Upgrading Project (PPSHUP) by M/s. SNC lavlin Inc., Canada. Before renovation the capacity of each machine was 12 MW.

Salient Features:

Location with district : Vellathooval, Idukki Dist.

Category : Hydro Power Project

Capacity :  50.8 MW

River : Muthirapuzha

Dam :Sengulam

Annual Energy Potential :  180 MU

Reservoir : Sengulam Balancing Reservoir

Catchment Area : 5.18 Sq. K.M (2. Sq. Miles)

Gross Storage : 2.31 MCM

Generation per MCM : 0.787 MU

Design Head : 343.4 Mts.

Full Reservoir level (FRL) :2780.01969 Ft. (847.35 M)

Min. Draw Down Level (MDDL) :2771.9816 Ft.

Design Disch. through Machine : 4.4802 M3/sec

Date of Commissioning:

Unit – 1 : 01.05.1954

Unit – 2 : 25.07.1954

Unit – 3 : 11.11.1954

Unit – 4 : 05.01.1955

Date of Rennovation:

Unit – 1 : 30.11.2002

Unit – 2 : 04.10.2002

Unit – 3 : 05.12.2001

Unit – 4 : 05.01.1955

Technical:

1. TURBINE

a) Type : Horizontal Axis Pelton Turbine

b) Make : ALSTOM CANADA INC. Granby Quebec, Canada

c) Design Net Head : 343.4Mts.

d) Rated Output :MW (6725 KW/runner nominal)

e) Output Max./ Min :…… MW/……. MW

f) Normal Speed :600 RPM

g) Runway speed :……… RPM

h) Disc. Through Machine : 4.4802 M3/sec

2. GENERATOR

a) Type : 3Ø Y SHZ/14/10/H

b) Make : ALSTOM- FRANCE

c) Rated Voltage : 11000 V

d) Rated Output : 14.111 KVA

f) Speed :600 RPM

g) Power Factor : 0.90

3. GENERATOR Transformers

a) Type :SOCRB

b) Make : TELK

c) Rated Voltage : 11kV/66kV

d) Rated Output : 15000 KVA

4. Power evacuation

a) 110kV NRSG feeder

110kV SGUD feeder

b) 66kV SGML feeder

    66kV SGPV feeder

c) 11kV – 4 nos feeders

Rating

Please rate us and give your valuable feedback if you are satisfied with this KSEBL website service.