Thottiyar HEP
Background:
Thottiyar Hydro Electric Project is a hydel scheme in the river Thottiyar (Deviyar) a tributary of river Periyar in Idukki district, Kerala State. The Project when completed (First Stage) will add an installed capacity of 40MW to the state grid.
Project Approval:
KSEBL accorded Revised Administrative Sanction on 19.11.2016 for Rs. 280 Crore at 2014 DSR with cost index 2015.
Contract for the Work:
The Original contract dated 22.12.2008 with M/s CPPL-Chongquing Joint Venture was foreclosed on 28.04.2017 due to slow progress. By then overall progress achieved was 33.80 %.
Contract for the balance Civil Work:
Balance Civil work was awarded to M/s. PRIL- SSIPL Consortium and agreement executed on 05.04.2018.
Agreed PAC - Rs. 97.76 Cr.
Actual date of commencement – 09.04.2018
Official date of completion - 03.04.2020
Progress achieved- 91.50%
Contract for the balance E&M Work:
E&M work awarded to M/s. Fitwell Constructions and agreement executed on 29.03.2021.
Agreed PAC Rs.6.79 Cr.
Actual date of Commencement – 10.07.2020
Official Date of Completion -10.04.2021
Progress achieved- 75%
Expected Completion of Project: 15.11.2023(1st Machine)