Capacity : 3x0.8 MW
Brief History:
Urumi Small Hydro Project Stage-II having an installed capacity of 2.4 MW (0.8 MW×3) is operated and controlled by Kerala State Electricity Board Ltd. Urumi SHEP stage-II is located at Urumi, a tributary if Poyilingapuzha river, which is a tributary of Iruvannjipuzha, which in turn is a tributary of Chaliyar in Thiruvambady Village, Kozhikode Taluk, Kozhikode district.
Salient Features:
Location with district : URUMI, KOZHIKODE
Category : Hydro Power Project (Small Hydro Electric Project)
Capacity : 2.4MW (3x0.8MW)
River : Poyilinga Puzha
Dam : Weir across the Poyilingapuzha river
Annual Energy Potential : 6.1MU
Reservoir :
Catchment Area : 16.67Sq. K.M (………. Sq. Miles)
Gross Storage : …. MCM
Generation per MCM : …….. MU
Design Head : 56Mts.
Full Reservoir level (FRL) : …… Ft. (……… M)
Min. Draw Down Level (MDDL) : ……… Ft.
Design Disch. through Machine : M3/sec
Date of Commissioning:
Unit – 1 : 10.10.2003.
Unit – 2 : 09.10.2003
Unit – 3 : 09.10.2003
Technical:
1. TURBINE
a) Type : Francis, Horizontal, Reaction
b) Make : ZHEJIANG JINLUN ELECTRO MECHANICAL CO LTD. CHINA
c) Design Net Head : 56Mts.
d) Rated Output : MW
e) Output Max./ Min : …… MW/……. MW
f) Normal Speed : 1000RPM
g) Runway speed : 2020RPM
h) Disc. Through Machine : 1.553M3/sec
2. GENERATOR
a) Type : Synchronous Generator
b) Make : HANGSHOU ELECTRICAL CHINA
c) Rated Voltage : 6300V
d) Rated Out put : KVA
f) Speed : 1000RPM
g) Power Factor : 0.8
3. GENERATOR TRANSFORMERS
a) Type : S9-3150/33
b) Make : ZHEJIANG ZANBIAN GROUP OF CO. LTD., THE PEOPLE REPUBLIC OF CHINA, 11/2001
c) Rated Voltage : 6300V/33000V
d) Rated Out put : 3150KVA
4. Power Evacuation
a)Feeder Name with voltage level (33kV Urumi-Thambalamanna