MANKULAM HEP
Background:
Mankulam Hydroelectric Project is located in Melachery river, a tributary of Periyar river. The scheme involves 55.10 sq.km catchment area of Melachery river. The scheme is proposed to construct a concrete gravity dam of 47.2m high across the Melachery river. The Mankulam scheme is proposed to develop in two stages. Stage – 1 consists of utilizing inflow of the free catchment 25.60 km² below Viripara diversion for generating 40 MW power and Stage – 2 involves diversion of adjacent rivers viz. Kadalar and Rajamalayar for another 40MW power generation in future. Construction activities of the Mankulam HEP stage -1 has been started.
Project Approval:
KSEBL accorded Administrative Sanction on 16.11.2021 for Rs.600 Crores at DSR 2016 Price Level.
Contract for the Civil Work:
Civil work awarded to M/s. PES – KSR Joint Venture, Hyderabad and agreement executed on 16.05.2022.
Agreed PAC - Rs. ₹ 250.22 Cr.
Actual date of commencement – 21.05.2022.
Official date of completion - 14.05.2026
Progress achieved – 6.02%
Expected Completion of civil Work: 14.05.2026.