Sengulam Augmentation Scheme
Background:
The scheme envisages diversion of water from Western Kallar to the existing reservoir at Sengulam by constructing a concrete weir just upstream of Kallar bridge across western Kallar stream. Water is proposed to be diverted through a ‘D’ shaped diversion tunnel taking off from upstream of the weir, to the Sengulam reservoir for augmenting the power generation at Sengulam Power House by 85 Mu.
Project Approval:
KSEB Ltd. accorded Revised Administrative Sanction on 16.03.2019 for Rs. 81.30 Crores based on 2016 price level.
Contract for the Civil Work:
Civil work awarded to M/s. Anchor Structurals Engineers & Contractors - M/s. UNIDEC Foundations (P) Ltd. Joint Venture (Erstwhile Dr. Sasi Eloor Engineers & Contractors - M/s. UNIDEC Foundations (P) Ltd. Joint Venture ) and agreement executed on 15.07.2009.
Agreed PAC - Rs. 41.65 Crore
Actual date of commencement – 06.07.2009
Official date of completion - 08.01.2013
Progress achieved- 76.95%
Expected Completion of Project: 31.03.2024.