|  Visit Old Website

LT Consumers

LT- 1- Domestic

Monthly
Consumption
Charge

Fixed Charge

Energy
Charge

Remarks

Rs./Consumer /Month
  Single
Phase
Three
Phase
   
0-40 Nil 1.50 This Rate is Applicable only for BPL Category
with Connected load of And below 1000W
0-50 40 100 3.25

Telescopic

51-100 65 140 4.05
101-150 85 170 5.10
151-200 120 180 6.95
201-250 130 200 8.20
0-300 150 205 6.40

Non-Telescopic

0-350 175 210 7.25
0-400 200 210 7.60
0-500 230 235 7.90
Above 500 260 260 8.80
0-50 40 100

1.50

BPL family having Cancer Patients or Permanently Disabled person as family members due to polio or accidents with Connected load of And below 1000W

51-100 65 140
ToD Tariff for Domestic Consumers with consumption above 500units
  Normal Period
( 06hrs to 18 hrs)
Peak Period
(18 hrs to 22 hrs)
Off Peak Period
(22 hrs to 06 hrs)

Six months consumtion shall be monitored from normal bi-monthly redings during January/February and July/August every year. If the average monthly for the first and second half of the year is above 500units, the consumer will be brought under ToD system after installing ToD meter in the premises.
Tod Based billing will be done whenever the monthly consumption exceeds 500units. If the consumtion falls below 500units/month, in any month , slab based billing shall be followed.

Energy Charge
(Rs./kWh)
100% of
the ruling tariff
120% of
the ruling tariff
90% of
the ruling tariff
LT- II- Temporary Connections
Energy Charge(Rs./kWh) 12.50
OR
Daily Minimum of Rs.100/kW or part thereof of the connected load, whichever is higher.
LT- III- Temporary Extensions
Fixed Charge per day -Rs.65/kW or part thereof of, the temporarily connected load plus the
Application fee,test fee etc. Energy charges shall be recovered from the consumer where from extension is availed , At the tariff applicable to him.
Note:Temporary extension shall be allowed only for a maximum period of 15 days at a time.
LT- IV(A) – Industry

Fixed
Charge

Connected load Of and below 10kW ( Rs. Per consumer per month) 140.00
Connected load above 10kW and upto 20kW ( Rs. Per kW per month) 85.00
Connected load above 20kW ( Rs. Per kVA or part thereof per month ) 200.00

Energy
Charge
(Rs./kWh)

Connected load Of and below 10kW 5.80
Connected load above 10kW and upto 20kW 5.80
Connected load above 20kW 5.85
General Conditions relating to installation of capacitors will apply
LT- IV(B) – IT AND IT Enabled Services

Fixed
Charge

Connected load Of and below 10kW ( Rs. Per consumer per month) 165.00
Connected load above 10kW and upto 20kW ( Rs. Per kW or part thereof per month) 120.00
Connected load above 20kW ( Rs. Per kVA or part thereof per month ) 200.00

Energy
Charge
(Rs./kWh)

Connected load Of and below 10kW 6.50
Connected load above 10kW and upto 20kW 6.50
Connected load above 20kW 6.60
General Conditions relating to installation of capacitors will apply
ToD Tariff for LT Industrial Consumers with
connected load of and above 20kW
  Normal Period
( 06hrs to 18 hrs)
Peak Period
(18 hrs to 22 hrs)
Off Peak Period
(22 hrs to 06 hrs)

Billing Demand during the month x demand charge per kVA

Energy Charge
(Rs./kWh)
100% of
the ruling tariff
150% of
the ruling tariff
75% of
the ruling tariff
Demand/Energy charges for LT industrial consumers with a connected load of and above 20KW , shall be as per the tariff approved in this schedule.
Power factor Incentive/disincentive
Above 0.95 and upto 1.0 ( incentive) 0.5% of the energy charges for each 0.01 unit increase in power factor from 0.95
0.90 and upto 0.95 (Penalty) 0.5% of the energy charges for every 0.01 fall in power factor below 0.95 and upto 0.90
Below 0.9 (Penalty) 1% of the energy charges for every 0.01 fall in power factor below 0.90
No Penalty and incentive for consumers with leading power factor.
LT-V(A)- Agriculture
Fixed Charge ( Rs. Per kW or part thereof per month) 20.00
Energy Charge ( Rs./kWh ) 2.30
General Conditions relating to installation of capacitors will apply
LT-V(B)- Agriculture
Fixed Charge ( Rs. Per kW or part thereof per month) 20.00
Energy Charge ( Rs./kWh ) 3.40
General Conditions relating to installation of capacitors will apply
LT-VI(A)- General(A)
Fixed Charge ( Rs. Per kW or part thereof per month) 80.00

Energy Charge
( Rs./kWh )
(Non Telescopic

Of and below 500 kWh (all units) 5.80
Above 500 kWh (all units) 6.65
LT-VI(B)- General(B)
Fixed Charge ( Rs. Per kW or part thereof per month) 105.00

Energy Charge
( Rs./kWh )
(Non Telescopic

Of and below 500 kWh (all units) 6.50
Above 500 kWh (all units) 7.15
LT-VI(C)- General(C)
Fixed Charge ( Rs. Per kW or part thereof per month) 190.00

Energy Charge
( Rs./kWh )
(Non Telescopic

Of and below 500 kWh (all units) 7.15
Above 500 kWh (all units) 8.65
LT-VI(D)- General(D)
Fixed Charge ( Rs. Per consumer per month) 35.00
Energy Charge ( Rs./kWh ) 2.10
LT-VI(E)- General(E)

Fixed Charge
( Rs. Per consumer
Per month)

Single Phase Consumers 50.00
Three Phase Consumers 120.00

Energy Charge
( Rs./kWh )
Non Telescopic

0 to 50 units per month 3.70
0 to 100 units per month 4.70
0 to 200 units per month 5.40
Above 200 units per month 7.10
LT-VI(F)- General(F)

Fixed Charge
( Rs. Per kW or part thereof
Per month)

Single Phase Consumers 90.00
Three Phase Consumers 180.00

Energy Charge
( Rs./kWh )
Non Telescopic

0 to 100 units per month 6.00
0 to 200 units per month 6.80
0 to 300 units per month 7.50
0 to 500 units per month 8.15
Above 500 units per month 9.25
LT-VI(G)- General(G)

Fixed Charge
( Rs. Per kW or part thereof
Per month)

Single Phase Consumers 80.00
Three Phase Consumers 165.00

Energy Charge
( Rs./kWh )
Non Telescopic

0 to 500 units per month 5.85
0 to 1000 units per month 6.60
0 to 2000 units per month 7.70
Above 2000 units per month 8.60
LT-VII(A)- Commercial(A)

Fixed Charge
( Rs. Per kW or part thereof
Per month)

Single Phase Consumers 90.00
Three Phase Consumers 175.00

Energy Charge
( Rs./kWh )
Non Telescopic

0 to 100 units per month 6.05
0 to 200 units per month 6.80
0 to 300 units per month 7.50
0 to 500 units per month 8.15
Above 500 units per month 9.40
LT-VII(B)- Commercial(B)

Fixed Charge
( Rs. Per kW or part thereof
Per month)

Connected load upto 1000W
(Rs. Per consumer/month)
60.00
Connected load above 1000W upto 2000W
(Rs. Per Kw/month)
70.00

Energy Charge
( Rs./kWh )
Non Telescopic

0 to 100 units per month 5.30
0 to 200 units per month 6.10
0 to 300 units per month 6.70
LT-VII(C)- Commercial (C)
Fixed Charge ( Rs. Per kW or part thereof per month) 130.00

Energy Charge
( Rs./kWh )
Non Telescopic

0 to 1000 units per month 6.30
Above 1000 units per month 7.70
LT-VIII(A)-Composite Tariff approved for Unmetered Street Lights

Type of Lamp

  Rs/lamp/month
Burning hours per day
4 hours 6 hours 12 hours
Ordinary 40 27 41 82
Ordinary 60 41 61 126
Ordinary 100 69 103 207
Fluro.tube 40 27 41 82
Fluro.tube 80 54 82 165
Flood Light 1000 691 1036 2073
MV Lamp 80 62 86 177
MV Lamp 125 94 138 275
MV Lamp 160 119 177 354
MV Lamp 250 184 275 552
MV Lamp 400 295 440 882
SV Lamp 70 52 79 155
SV Lamp 80 59 86 177
SV Lamp 100 73 110 220
SV Lamp 125 94 138 275
SV Lamp 150 110 165 331
SV Lamp 250 184 275 552
SV Lamp 11 6 10 20
CFL 14 8 12 26
CFL 15 9 14 27
CFL 18 11 16 32
CFL 22 14 20 40
CFL 30 19 27 54
CFL 36 22 32 66
CFL 44 26 40 79
CFL 72 44 66 130
CFL 144 86 130 259
CFL 9 3 5 12
LED 12 5 6 17
LED 15 6 8 22
LED 18 6 14 25
LED 20 9 14 28
LED 24 12 17 37
LED 25 12 17 39
LED 30 14 20 47
LED 35 16 25 48
LED 40 19 28 56
LED 45 20 30 66
LED 70 33 48 98
LED 80 36 56 112
LED 110 50 78 153
LED 150 69 106 209
MV Lamp on semi high mast only for 12 hrs burning per day 1200     2669
SV Lamp on semi high mast only for 12 hrs burning per day 250     556
LT-VIII(B)- Metered street lights and Traffic Signal Lights
Fixed Charge ( Rs. Per meter per month) 90.00
Energy Charge ( Rs./kWh ) 4.80
LT-IX- Display Lighting and Hoardings

Fixed Charge

( Rs. Per Connection per month upto 1kW 700.00
For every additional 1kW,
Above 1kW (Rs./kW /month
150.00
Energy Charge ( Rs./kWh ) 12.50
LT-X- Electric Vehicle Charging Stations
Fixed Charge ( Rs. Per kW or part thereof per month) 100.00
Energy Charge ( Rs./kWh ) 5.50

Rating

Please rate us and give your valuable feedback if you are satisfied with this KSEBL website service.