1. |
Service Name |
Meter shifting |
2. |
Description of the service |
Shifting of meter/service line within the premises of the consumer after completion of the following pre-requisites:
- Complete the installation of the meter board with proper earthing at the location to where the meter is to be shifted.
|
3. |
Eligibility conditions of applicant for availing the service (if any) |
- The applicant should be the legal owner/tenant/occupant of the property/building.
|
4. |
Fees applicable and payment options available |
- SINGLE PHASE: Application fees: Rs. 10/- plus GST; Labour charge: Rs. 300 plus GST; IF/TF: Rs. 25/- plus GST.
- THREE PHASE: Application fees: Rs. 10/- plus GST; Labour charge: Rs. 500 plus GST; CT meter (LT): Rs. 1,200/-; TOD Meter: Rs.1,800/- plus GST; IF/TF: Rs. 50/- plus GST.
|
5. |
Designated Officer/Office for service delivery |
Assistant Engineer of the concerned section office |
6. |
Online application processing procedure and process flow |
- Create an account with KSEBL by registering in the KSEBL Web Self-Service Portal - wss.kseb.in.
- Apply for meter shifting by logging in and uploading the necessary documents.
|
7. |
Service timeline |
- Shifting of LT service line: Thirty days from the date of remittance of the demand
- Shifting of HT service line: Forty-five days from the date of remittance of the demand
- Shifting of transformer: Thirty days from the date of remittance of the demand
|
8. |
Comprehensive list of required documents |
- Proof of Identity
- Test cum Completion certificate issued by a licensed contractor.
- Sketch showing the present and proposed location.
|
9. |
Contact details of the supporting officer (including Telephone No and Email ID) |
Concerned Section Office / 1912 (Tollfree Customer Care number) |