Board Orders
199/2023 (Estt.IV/6848/2022)
Establishment - Reckoning of prior service rendered elsewhere by the Board employees for pensionary benefits- Modification of Board Order
Date: 2023-04-13198/2023(DIRDIT-AE2/Works /2022/006)
Execution of work for laying 5.2km 11kV UG cable, 5 km LT ABC with 100 LED streetlight installation, installing 84 nos. RMU along with dismantling of existing HT/LT OH line
Date: 2023-04-13195/2023(DIRDIT-AE2/Utility Shifting/2022-23/002)
Shifting of utilities in connection with the construction of 6 lane Elevated Highway along with the development of existing 4 lane road at ground level from Aroor to Thuravoor
Date: 2023-04-13194/2023(DIRGE-AEE1/2023/197)/21
Sabarigiri HEP- Unit 2 -Design,Supply,Dismantling, Supervision of Erection, Testing & Commissioning of Stator rewinding and stator Core re-varnishing
Date: 2023-04-12192/2023(DGC/AEE I/TENDER/GCC/2022)
Review and refinement of General Conditions of Contract applied to Civil Procurement-Adoption of CPWD General Conditions of Contract
Date: 2023-04-11193/2023(DIRTSO-AE6/2022/2318)
Power evacuation from Thottiyar HEP by constructing 400 meter 220kV DC line as LILO from Lower Periyar- Madakkathara feeder - Re-tender invited - Tender excess
Date: 2023-04-11188/2023(DGC/AEEVI/PSR/2014)
Execution of Civil Works of Pazhassi Sagar SHEP 7.5MW (3X2.5MW)-25.16MU-Contract with M/s R.S Development and Constructions India (P) Ltd, Erode
Date: 2023-04-10189/2023(COM-AEE8/2023/13)
Management of power deficit - Inviting short term tender through DEEP portal as per MoP guidelines, for meeting the power deficit during peak hours of May 2023
Date: 2023-04-10187/2023(COM-AEE8/2023/13)
Managing power crisis during peak hours of May 2023 - floating tender in DEEP portal on 20.02.2023 - Outcome of bid - Recommendation of the Standing Committee
Date: 2023-04-10183/2023(DGE/G3/Neriyamangalam WG repl.)
Replacement of Wicket Gate cup seal of Neriamangalam Machines - Sanction for availing spares and services through the OEM, M/s. Andritz Hydro
Date: 2023-04-05185/2023(DIRGE/AEE4/PGL-SHEP/2022)
Execution of Electro and Hydro mechanical works of Poringalkuthu (1x24 MW) SHEP - Time extension for the Period of the Contract
Date: 2023-04-05180/2023(DIRDIT-AE2/OTS/2022/003)
Request for HT connection to M/s.Leprosy Sanatorium, Nooranadu, under Electrical Section, Charummoodu, Electrical Circle, Haripad
Date: 2023-04-05179/2023 (SOR/AMU 8/HTB 20/1985/2022-23)
M/s. Usha Polymers Pvt. Ltd. (defunct) (LCN 20/1985), Muttom, Thodupuzha - Withdrawal of demand from books of account
Date: 2023-04-04178/2023(CE(SCM)/XH-AE1/2022-23/11kV XLPE UG Cable/Gupta)
Supply of 11kV,3x300 sq.mm XLPE UG cable by M/s. Gupta Power infrastructure Limited - Delivery extension granted - Price refixation done in Additional order clarified
Date: 2023-04-04177/2023 (IT/Proj/RDSS/Smart Meter/2022-23)
Revamped Distriibution Sector Scheme (RDSS) – lmplementation of Prepaid Smart meter in KSEBL - Fresh tender to be invited
Date: 2023-04-01176/2023 [PS1(A)/OLGT-2023/GL for Higher Level Officers]
Guidelines for Online General Transfer of the Higher Level Officers - Approved
Date: 2023-03-31174/2023/CE(REES)/CP/BAK/2020-21
Design, Erection, Testing & commissioning of Grid tied Ground mounted solar PV Power plants at Brahmapuram, Kanjikode and Agali owned by KSEBL
Date: 2023-03-31171/2023(DGC/AEEV/PES-Intake/2017)
Pallivasal Extension Scheme (2x30MW) - Expression of Interest and Request for Proposal for Engineering design, construction works of intake structure
Date: 2023-03-31170/2023(DGC/AEEV/PES-Balance works/2018)
Pallivasal Extension Scheme (2x30 MW) - Balance Civil Works of Tunnel, Surge Shaft, Pressure Shaft, Penstock, Power House and Allied Works
Date: 2023-03-31175/2023 (SCM/XM/Tech Committee Distn/2022-23)
Reconstitution of 'Technical Specification and Evaluation Committee for Distribution items'
Date: 2023-03-31172/2023(DGC/AEEII/Seng.Penstock/2022)
Execution of rectification/replacement of penstocks, butterfly valves, gate valves and allied works of Sengulam HEP - Time extension
Date: 2023-03-31164/2023(ITCU/Life Certificate/2022-23)
Implementation of Jeevan Praman - Life certificate for KSEBL Pensioners
Date: 2023-03-31169/2023(DGC/AEEIII/MKLM/2014)
Mankulam Hydro Electric Project (40 MW) - Execution of Civil Works - Utilizing Land / Yard Facilities at Valara
Date: 2023-03-31168/2023(No.DGC/AEEIII/Thottiyar/2014)
Execution of Balance Civil & Hydro Mechanical Works of Thottiyar Hydro Electric Project- Contract with M/s. P&R INFRA Projects Ltd. & M/s. Shri Saravana Industries Pvt Ltd.
Date: 2023-03-31167/2023(DGC/AEEIII/thottiyar/2014)
Execution of Balance Civil and Hydro Mechanical Works of Thottiyar Hydro Electric Project (40 MW/ 99 Mu) - Contract with M/s PRIL-SSIPL Consortium
Date: 2023-03-31166/2023(No.DGC/AEEIII/Thottiyar/2014)
Execution of Balance Civil and Hydro Mechanical works of Thottiyar Hydro Electric Project (40 MW/99 Mu) - contract with M/s PRlL-SSIPL Consortium
Date: 2023-03-31162/2023 (Estt.II/1236/2023)
Establishment - Compassionate Employment Scheme — Appointment of dependants of KSEBL employees who die-in-harness—Select List for 02/2023—Approved
Date: 2023-03-31161/2023 (CSC/AE2/FTD/2022-23)
Budget for the period from FY 22-23 to FY 26-27 under safety wing - Inter departmental coordination
Date: 2023-03-31156/2023 (CE(SCM)/XH-AE1/2022-23/2.5sq.mm & 6 Sq.mmWP /Bhadora)
WP(C) No. 5276/2023 filed by M/s. Bhadora Industries Pvt. Ltd challenging the act on the part of KSEBL passing the Board order dated 03.12.2022
Date: 2023-03-27148/2023(DIRTSO-AE5/2022/3118)
TransGrid 2.0 - GIS package II - Construction of 400kV GIS, Kottayam - Contract with M/s Toshiba Transmission & Distribution Systems India Pvt Ltd.
Date: 2023-03-25154/2023(DIRGE-AEE4/2023/200)
Thottiyar HEP- Supply, Erection, Testing and Commissioning of Governor, Excitation, DCS and Protection panels - Request for time extension
Date: 2023-03-25151/2023(DIRGE-AEE4/2023/204)
Commissioning of Poringalkuthu SHEP (1x24MW) - Good Service Entry - Appreciation
Date: 2023-03-25150/2023(D(T&SO)/T7/Land-Wayanad/2021-22)
Implementation of North Green Corridor project - Construction of 400kV Substation, Payyampally - Land to be acquired through LARR Act
Date: 2023-03-25152/2023(DIRTSO-AEE3/2022/2349)
Advanced training program conducted on SAS & DlGSl 5 Engineering Tool at Siemens Power Academy, Goa for the officers of KSÉBL - Effecting payment from KSEBL fund
Date: 2023-03-25153/2023(No.DGC/AEEIV/SAS/2014)
Sengulam Augmentation Scheme (85 Mu) - Formation of Standing Technical Committee
Date: 2023-03-25143/2023 (No.CML-EE-2-AEE-2/CE(C&T)/Mukkudam-SHEP/2022-23)
Mukkudam 4 MW SHEP by M/ s Mukkudam Electro Energy Pvt Ltd- Approving and initialling Modified draft PPA
Date: 2023-03-23145/2023(DIRGE-AEE4/2023/184)
PES & THEP - Supply, Laying, Testing and Commissioning of 220 kV, 800 sq.mm XLPE, underground cable for power evacuation from PES HEP and 220 kV, 500 sq.mm XLPE
Date: 2023-03-23144/2023(KSEB/TRAC-AEE2)/2023/68
KSERC Order dated 23.2.2023 on APPC of KSEBL - Implementing KSERC order
Date: 2023-03-23142/2023(DIRTSO-AE6/2022/3339)
Construction of 110 kV Substation at Murikkassery and 5.5 km 110kV DC line
Date: 2023-03-21141/2023(D(T&SO)/T4/Solar-Cheemeni/2020-21)
100 MW Solar Park at Cheemeni - Commitment of KSEBL to purchase 100% power from the project
Date: 2023-03-21