189/2023(COM-AEE8/2023/13)

Management of power deficit - Inviting short term tender through DEEP portal as per MoP guidelines, for meeting the power deficit during peak hours of May 2023

Date: 2023-04-10

187/2023(COM-AEE8/2023/13)

Managing power crisis during peak hours of May 2023 - floating tender in DEEP portal on 20.02.2023 - Outcome of bid - Recommendation of the Standing Committee

Date: 2023-04-10

183/2023(DGE/G3/Neriyamangalam WG repl.)

Replacement of Wicket Gate cup seal of Neriamangalam Machines - Sanction for availing spares and services through the OEM, M/s. Andritz Hydro

Date: 2023-04-05

185/2023(DIRGE/AEE4/PGL-SHEP/2022)

Execution of Electro and Hydro mechanical works of Poringalkuthu (1x24 MW) SHEP - Time extension for the Period of the Contract

Date: 2023-04-05

180/2023(DIRDIT-AE2/OTS/2022/003)

Request for HT connection to M/s.Leprosy Sanatorium, Nooranadu, under Electrical Section, Charummoodu, Electrical Circle, Haripad

Date: 2023-04-05

179/2023 (SOR/AMU 8/HTB 20/1985/2022-23)

M/s. Usha Polymers Pvt. Ltd. (defunct) (LCN 20/1985), Muttom, Thodupuzha - Withdrawal of demand from books of account

Date: 2023-04-04

178/2023(CE(SCM)/XH-AE1/2022-23/11kV XLPE UG Cable/Gupta)

Supply of 11kV,3x300 sq.mm XLPE UG cable by M/s. Gupta Power infrastructure Limited - Delivery extension granted - Price refixation done in Additional order clarified

Date: 2023-04-04

177/2023 (IT/Proj/RDSS/Smart Meter/2022-23)

Revamped Distriibution Sector Scheme (RDSS) – lmplementation of Prepaid Smart meter in KSEBL - Fresh tender to be invited

Date: 2023-04-01

176/2023 [PS1(A)/OLGT-2023/GL for Higher Level Officers]

Guidelines for Online General Transfer of the Higher Level Officers - Approved

Date: 2023-03-31

174/2023/CE(REES)/CP/BAK/2020-21

Design, Erection, Testing & commissioning of Grid tied Ground mounted solar PV Power plants at Brahmapuram, Kanjikode and Agali owned by KSEBL

Date: 2023-03-31

171/2023(DGC/AEEV/PES-Intake/2017)

Pallivasal Extension Scheme (2x30MW) - Expression of Interest and Request for Proposal for Engineering design, construction works of intake structure

Date: 2023-03-31

170/2023(DGC/AEEV/PES-Balance works/2018)

Pallivasal Extension Scheme (2x30 MW) - Balance Civil Works of Tunnel, Surge Shaft, Pressure Shaft, Penstock, Power House and Allied Works

Date: 2023-03-31

175/2023 (SCM/XM/Tech Committee Distn/2022-23)

Reconstitution of 'Technical Specification and Evaluation Committee for Distribution items'

Date: 2023-03-31

172/2023(DGC/AEEII/Seng.Penstock/2022)

Execution of rectification/replacement of penstocks, butterfly valves, gate valves and allied works of Sengulam HEP - Time extension

Date: 2023-03-31

164/2023(ITCU/Life Certificate/2022-23)

Implementation of Jeevan Praman - Life certificate for KSEBL Pensioners

Date: 2023-03-31

169/2023(DGC/AEEIII/MKLM/2014)

Mankulam Hydro Electric Project (40 MW) - Execution of Civil Works - Utilizing Land / Yard Facilities at Valara

Date: 2023-03-31

168/2023(No.DGC/AEEIII/Thottiyar/2014)

Execution of Balance Civil & Hydro Mechanical Works of Thottiyar Hydro Electric Project- Contract with M/s. P&R INFRA Projects Ltd. & M/s. Shri Saravana Industries Pvt Ltd.

Date: 2023-03-31

167/2023(DGC/AEEIII/thottiyar/2014)

Execution of Balance Civil and Hydro Mechanical Works of Thottiyar Hydro Electric Project (40 MW/ 99 Mu) - Contract with M/s PRIL-SSIPL Consortium

Date: 2023-03-31

166/2023(No.DGC/AEEIII/Thottiyar/2014)

Execution of Balance Civil and Hydro Mechanical works of Thottiyar Hydro Electric Project (40 MW/99 Mu) - contract with M/s PRlL-SSIPL Consortium

Date: 2023-03-31

162/2023 (Estt.II/1236/2023)

Establishment - Compassionate Employment Scheme — Appointment of dependants of KSEBL employees who die-in-harness—Select List for 02/2023—Approved

Date: 2023-03-31

161/2023 (CSC/AE2/FTD/2022-23)

Budget for the period from FY 22-23 to FY 26-27 under safety wing - Inter departmental coordination

Date: 2023-03-31

156/2023 (CE(SCM)/XH-AE1/2022-23/2.5sq.mm & 6 Sq.mmWP /Bhadora)

WP(C) No. 5276/2023 filed by M/s. Bhadora Industries Pvt. Ltd challenging the act on the part of KSEBL passing the Board order dated 03.12.2022

Date: 2023-03-27

148/2023(DIRTSO-AE5/2022/3118)

TransGrid 2.0 - GIS package II - Construction of 400kV GIS, Kottayam - Contract with M/s Toshiba Transmission & Distribution Systems India Pvt Ltd.

Date: 2023-03-25

154/2023(DIRGE-AEE4/2023/200)

Thottiyar HEP- Supply, Erection, Testing and Commissioning of Governor, Excitation, DCS and Protection panels - Request for time extension

Date: 2023-03-25

151/2023(DIRGE-AEE4/2023/204)

Commissioning of Poringalkuthu SHEP (1x24MW) - Good Service Entry - Appreciation

Date: 2023-03-25

150/2023(D(T&SO)/T7/Land-Wayanad/2021-22)

Implementation of North Green Corridor project - Construction of 400kV Substation, Payyampally - Land to be acquired through LARR Act

Date: 2023-03-25

152/2023(DIRTSO-AEE3/2022/2349)

Advanced training program conducted on SAS & DlGSl 5 Engineering Tool at Siemens Power Academy, Goa for the officers of KSÉBL - Effecting payment from KSEBL fund

Date: 2023-03-25

153/2023(No.DGC/AEEIV/SAS/2014)

Sengulam Augmentation Scheme (85 Mu) - Formation of Standing Technical Committee

Date: 2023-03-25

143/2023 (No.CML-EE-2-AEE-2/CE(C&T)/Mukkudam-SHEP/2022-23)

Mukkudam 4 MW SHEP by M/ s Mukkudam Electro Energy Pvt Ltd- Approving and initialling Modified draft PPA

Date: 2023-03-23

145/2023(DIRGE-AEE4/2023/184)

PES & THEP - Supply, Laying, Testing and Commissioning of 220 kV, 800 sq.mm XLPE, underground cable for power evacuation from PES HEP and 220 kV, 500 sq.mm XLPE

Date: 2023-03-23

144/2023(KSEB/TRAC-AEE2)/2023/68

KSERC Order dated 23.2.2023 on APPC of KSEBL - Implementing KSERC order

Date: 2023-03-23

142/2023(DIRTSO-AE6/2022/3339)

Construction of 110 kV Substation at Murikkassery and 5.5 km 110kV DC line

Date: 2023-03-21

141/2023(D(T&SO)/T4/Solar-Cheemeni/2020-21)

100 MW Solar Park at Cheemeni - Commitment of KSEBL to purchase 100% power from the project

Date: 2023-03-21

140/2023(No.DGC/AEEIII/Thottiyar/2014)

Execution of Balance Civil & Hydro Mechanical Works of Thottiyar Hydro Electric Project -Contract with M/s.P&R INFRA Projects Ltd. & M/s. Shri Saravana Industries Pvt Ltd.

Date: 2023-03-21

138/2023 (XD/AE1/SCM/eP19/2022-23)

Procurement of LT Aerial Bunched Cables of various Srzes - Placing Purchase Order

Date: 2023-03-18

137/2023 (CE(SCM)/XH-AE3/2022-23/ACSR conductor/eP.34)

Purchase of 12500 km of XLPE insulated ACSR Rabbit Conductor - Finalization of Tender

Date: 2023-03-18

136/2023 (Estt.II/963/2023)

Establishment - Compassionate Employment Scheme — Appointment of dependants of KSEBL employees who die-in-harness — Select List for 01/2023 - Approved

Date: 2023-03-17

132/2023(DGC/AEE-VI/BRPL/2014)

Barapole SHEP (15MW) - Remedial measures for power canal of Barapole SHEP - lmplementation of recommendation of IIT Roorkee - Providing filter arrangement

Date: 2023-03-16

131/2023 (FA/AA/Limited review/2022-23)

Ministry of Power - Directions to State DISCOMS on model corporate governance Limited review on quarterly basis - Quarterly accounts- approved

Date: 2023-03-16

130/2023 (FA/AA/Audit Qualification-Depreciation/2022-23)

Audit qualification of Statutory Auditors for the Financial Year 2021-22- providing depreciation during 2022-23