150/2024 (DGC/AEE IV/SAS/2014)

Sengulam Augmentation Scheme (85 Mu) - Construction of a concrete gravity weir across Western Kallar, Intake arrangements, Diversion Tunnel, Exit Channel

Date: 2024-04-11

146/2024 (CEIT/RITU/SCADA-PM)

Implementation of RDSS SCADA Projects in KSEBL - Formation of field implementation team with strategical units - Sanctioned - Orders issued

Date: 2024-04-11

144/2024 (DGE/G2/AEE3/SHOLAYAR-RMU/2023)

Renovation & Modernization (R&M) Work of Sholayar Hydro Electric Project (3x18 MW): Issues with M/s. FEPL (FLOVEL) - Sanctioned

Date: 2024-04-09

140/2024 (DGC/AEEV/PES-Balance works/2018)

Pallivasal Extension Scheme (2X30 MW) - Balance Civil Works of Tunnel, Surge Shaft, Pressure Shaft, Penstock, Power House and Allied Works

Date: 2024-04-05

139/2024 (DGC/AEEV/Pallivasal/Ext.pipe/2020)

Pallivasal Hydro Electric Scheme (37.5 MW) - Extending 1600mm dia penstock from Anchor Block A9 of PES to the existing Pallivasal Power House

Date: 2024-04-05

138/2024 (E.20219/Fin2(B)/TMB/IB/OD-WCDL/2023-24)

Renewal of Credit limit of ₹75 Crore from M/s Tamilnad Mercantile Bank Limited, Thiruvananthapuram - Sanctioned - Orders issued

Date: 2024-04-05

141/2024 (DGC/AEEV/PES-Intake/2017)

Pallivasal Extension Scheme (2 X 30 MW) - Expression of Interest and Request for Proposal for Engineering design, construction works of intake structure

Date: 2024-04-05

125 /2024 (No.CML-EE-2-AEE-2/CE(C&T)/Pathamkayam /2023-24)

Pathamkayam SHEP (8MW) by M/s MINAR Energy Projects Pvt. Ltd.-Exit clause-Further decisions - Sanctioned

Date: 2024-03-30

127/2024 (No.E.19528/Fin2 (B)/IB Federal Bank/OD/WCDL/2023-24)

Renewal and enhancement of credit facilities to Rs.475 Crores from M/s.Federal bank -Sanctioned - Orders issued

Date: 2024-03-30

132/2024 (SOR/AMU 4/HTB 21/3655/2023)

Settlement of current charge arrears of M/s. BGR Hotels (P) Ltd (LCN. 21/3655) under OTS Scheme 2023 - Sanctioned - Orders issued

Date: 2024-03-30

134/2024 (SOR/HTB/31/3805/2023)

Settlement of current charge arrears of M/s. Lausam Steel Rolling Mill (LCN 31/3805) under One Time Settlement Scheme 2023 - Sanctioned

Date: 2024-03-30

129/2024 (CS-KSEBL-Independant Director /2015-16)

Appointment of Prof. Arun Kumar in the Board of Directors of KSEBL as Independant Director- Reconstitution of Audit Committee & CSR Committee

Date: 2024-03-30

130/2024(E395/KSEBL/FA/AAA/25/2024-S1)

Withdrawal of KWA arrears taken over by the Government as on 31.10.2023 - Sanctioned -Orders issued

Date: 2024-03-30

124/2024 (LAWIII/6398/2023)

WP(C) No.26889/2023 before the Hon'ble High Court of Kerala - Filed by Rojer Mathew and another -Request of the petitioner to remit the arrears in instalments

Date: 2024-03-27

123/2024 (No. CML-EE-2-AEE-2/CE(C&T)/Palakuzhy

Initialing of Power Purchase Agreement (PPA) with Palakkad Small Hydro Company Ltd for procuring power from Palakuzhy SHEP (1MW) - further negotiations reg

Date: 2024-03-27

121/2024 (DGC/AEEIV/Dam safety/Vehicle/2023)

Sholayar HEP- Enhancing the monthly ceiling limit of department vehicle attached to Dam Safety Section, Sholayar from 1500 km to 2000 km - Sanction - Accorded

Date: 2024-03-26

120/2024 (CE(SCM)/ XH-AEE4/2023-24/ACSR conductor/SD/MSME)

Purchase order for the supply of ACSR Raccoon and Rabbit Conductors - Releasing of Permanent Security Depoist furnished by the local MSMEs - Sanctioned

Date: 2024-03-26

118/2024 (No.CML-EE-2-AEE-2/CE(C&T)/Pathamkayam/2023-24)

Pathamkayam SHEP 8MW -KSERC approved PPA -Decision on Exit Clause & releasing difference amount - Sanctioned - Orders issued

Date: 2024-03-23

CS/KSEBL/Independent Director/2015-16

Independent Director Appointment

Date: 2024-03-19

116 /2024 (KSEBL/SEC/ESTT/158/2024-S4)

Establishment - Request for Voluntary Retirement in respect of Sri Anil Kumar S (1037489), Deputy Chief Engineer (Civil), O/o the Chief Engineer Spin & Consultancy

Date: 2024-03-19

117/2024 (DGC/AEEV/Up-Seng/2015)

Execution of Civil and Hydro Mechanical works of Upper Sengulam Hydro Electric Project (1x24MW/53.22Mu) - Amendment in Letter of Acceptance

Date: 2024-03-19

115/2024 (DIRTSO - AE1/Kothakurussi -land/2023-24)

Construction of 110kV Substation Kothakurussi in Palakkad district - Taking over 0.4629 Ha of land from Revenue and Irrigation Departments on lease basis

Date: 2024-03-13

114/2024 (DGC/AEE IV/Apartment for Directors/2022)

Hiring of residential apartments for the accommodation of Directors of KSEBL - Renewal of lease agreement of apartment at Nanthancode - Sanctioned

Date: 2024-03-13

103/2024 (DIRTSO/AE4/Tree cutting -Mylatty/2023-24)

Cutting and removal of trees (617 nos) in the compound of 220kV Substation Mylatty for the implementation of 3.5 MWp solar plant under PMKUSUM scheme

Date: 2024-03-11

105/2024 (DGE/G2/AEE3/Pazhassi Sagar/2023)

Pazhassi Sagar SHEP (3 x 2.5 MW) - Allocation of space for construction of temporary store and meeting expenses due to delay in completion of project

Date: 2024-03-11

106/2024 [D(T,SO&P)/T1/VSSC/GIC/2023-24/I/21842]

Field testing of Sensor for Ge-magnetically Induced Currents (GICs) in power system developed by M/s Space Physics Laboratory, VSSC

Date: 2024-03-11

104/2024 (KSEBL/SEC/ESTT/61/2024-S2)

Establishment - Compassionate Employment Scheme - Appointment of dependants of KSEBL employees who die-in-harness -Select List for 11/2023 - Approved

Date: 2024-03-11

111 /2024 (CE(C&T)/Solar- short term power purchase/2023-24)

Final order on the petition filed by M/s CIAL infrastructures Ltd seeking extension of short term power purchase contract with KSEBL dated 16.12.2022

Date: 2024-03-11

109/2024 (CE(C&T)/CML/EE-2/Short term tender-4/2023-24)

Management of power deficit during April & May 2024 - Short term tender invited through DEEP portal as per MoP guidelines - Sanctioned

Date: 2024-03-11

113/2024(SC-AEE1/2023/5)

Sports Cell - By transfer appointment to Sri.Ajay Satish Kumar Nair, Office Attendant Gr-II, O/o the CIA & member of the KSEB Badminton team

Date: 2024-03-11

101/2024 (DIRTSO-AE4/2023/1902)

Construction of 110kV Substation Pavandoor in Kozhikode district - Acquisition of 129.99 cents of land in Thalakulathoor village, Kozhikode district - Sanctioned

Date: 2024-03-07

100/2024 (KSEBL/SEC/ESTT/32/2024-S2)

Compassionate Employment Scheme - Approval of candidates nominated for the post of Office Attendant Grade II as per the Select List

Date: 2024-03-05

96 /2024 (No. CE(C&T)/ Long term power procurement/2023-24)

Long term procurement of power due to increase in power demand and non-scheduling of generators of existing long term DBFOO contract -Sanctioned

Date: 2024-03-04

97 / 2024 [LAIV /8483 / 2016]

Conduct of KSEBL's cases before the Hon'ble High Court of Kerala- Appointment of Standing Counsel- Sanctioned

Date: 2024-03-04

99/2024 (VIG/B1/6889/2002)660

Demand and acceptance of bribe - Criminal case against Sri.T.C.Yohannan, then Sub Engineer of Electrical Major Section, Puthanathani

Date: 2024-03-04

FTD No.91/2024(DIRDIT)/AE5/2023/LOAD

Voluntary Declaration of Connected Load-Extending scheme.

Date: 2024-03-02

92/2024(SOR-SS1/2023/1073)

Settlement of current charge arrears of M/s Hindalco Industries Limited (LCN 3/325), under OTS Scheme 2023 - Sanctioned

Date: 2024-03-02

90/2024(DIRDIT-AE7/2023/10616)

Sanction for hiring a Contract Jeep with a monthly limit of 1750km from the existing 1500km attached to Electrical Section, Angamaly under Electrical Circle, Perumbavoor

Date: 2024-03-02

88/2024 (Fin 2(A)/REC-STL-200Cr/2024)

Availing of the Short Term Loan of Rs.200 Crore from M/s REC Limited- Sanctioned -Orders issued

Date: 2024-02-29

87/2024 (DGE/G2/AEE3/PESHEP/2023)

Pallivasal Extension Scheme HEP (2x30 MW) - Erection of supplied E&M Equipment and supply and erection of Balance of Plant equipment

Date: 2024-02-26